Approximate
Timetable 2003 (rev 9/25/03)
Initial
mtg with DTNNA/Unblock Committee 9/8 –
9/19
DTNNA
Big Mtg 9/18
Gather
evaluation data (including all counts) 9/10 -
10/15
DTNNA
Small Mtgs (?) 9/22 – 9/24
Begin
PTC Report 10/13
City’s
neighb mtg announcement to repro 10/15
Mail
neigb mtg announcment 10/22
Propose
and evaluate mods to plan and survey content. Review with joint w.g. 10/15 - 10/22
Neighborhood
groups pre-survey outreach 10/22-11/12
Prepare
survey and evaluation letter 10/29 –
11/5
Survey
and letter to repro 11/5
City’s
Neighb Mtg 11/6
Mail
survey and letter 11/12
Prepare
resident notifcation ltr for PTC mtg 11/19
Survey
cards due back 11/24
Extra
survey return outreach 11/24 – 12/2
Res
notification ltr for PTC report and mtg to repro 11/25
CS
Finish staff report 12/4
Steve,
Joe review PTC report 12/4
– 12/9
Mail
ltr to residents to announce report and PTC mtg 12/3
PTC
report to repro (Does not allow extra lead time for public review) 12/10
Citizen
comments deadline for packet 12/10
PTC
report available to public and in packet 12/12
PTC
special meeting (verify) 12/17
21
day EA Circulation (verify with Wynne if needs to be before PTC) 12/22-1/16
CC
meeting Late Jan